Task List (1)



Test Software


Task Months When Who
Test vectors for single module tests 2 Tests WNS
Test vectors (simulated data) for slice test 1? Slice ?
HDMC development (new Parts?) 1? Slice ?
Actually testing the modules:
CPROD (3 * CP firmware) 3 Tests BB
CPROD (5 * JEP firmware) 1 Tests ?
CPM 2 Tests GM?
CMM 2 Tests NG?
JEM 2 Tests JT?
PPROD 2 Tests [HD]
PPM 2 Tests [HD]



System Setup


Task Months When Who
Databases: hardware configuration, calibrations, trigger menu 2 Slice ML+?
Run controller framework 1 Slice ML
IS classes for run parameters, crate and module status 1 Slice ML
IGUI panel(s) 1 Slice ML
Hardware access library (developing HDMC framework) 1 Slice ?
Module actions 2 Slice ML+?