next up previous



Software Status

Murrough Landon - 7 March 2003
http://www.hep.ph.qmul.ac.uk/landon/talks



Overview



Reminder of the Aims

Slice Test Procedure



Recent Developments: Overview

Since the first release



Recent Developments: Database (1)

Better support for run types



Recent Developments: Database (2)

Firmware

TTCvi



Recent Developments: Database/Run Control

Better support for multistep runs

Cleanup



\begin{htmlslide}[L1Calo Components and Packages]
\begin{center}
\begin{figu...
...cale=0.385]{figures/PkgOverviewL.eps} \end{figure} \end{center}
\end{htmlslide}


Whats missing? (1)

General framework

CP subsystem



Whats missing? (2)

JEP subsystem



Whats missing? (3)

PP subsystem



Whats missing? (4)

System environment



Rough summary


Activity Core ROD CP JEP PP Slice
Database 90% 90% 80% 80% 50% 70%
Test vector gen 90% 90% 80% 50% 30% 50%
Simulation 90% 90% 90% 40% 20% 50%
Load hardware 90% 90% 80% 80% 20% 70%
Run control 80% N/A N/A N/A N/A 80%
Read out data 50% 90% N/A N/A N/A 10%
Display results 60% 90% 60% 50% 10% 40%
Diagnostics 90% 90% 80% 90% 20% 40%
Monitor h/w 70% 20% 20% 20% 10% 10%
Calibration 40% N/A 40% 20% 10% 20%
Event dump/disp 50% 20% 20% 20% 0% 10%



Timescales...eg CPROD tests

CPROD tests



Tasks and Timescales (1)

Core and infrastructure


Activity Duration Date        
Test/debug new database features 1 week? March?        
Multistep runs with test vectors 1 week? March?        
Test and use L1A generation via DSS 2 weeks? April?        
``allModules'' package 1 week? March/April?        
System upgrades 2 weeks? April????        
Use ROS (2 RODs) 1 month? May??        
Use monitoring framework 1 week? May??        
Report hardware status via the IGUI 1 week? April?        

NB above assumes virtually no more ROD testing required!



Tasks and Timescales (2)

CP/JEP Subsystems


Activity Duration Date        
CPM services and test programs 1 month? April?        
CMM services and test programs 1 month? April?        
CMM simulation (inc JEP variants) 1 month? May?        
JEM services and test programs 1 month? April?        
JEM simulation 2 months? May/June??        
CP/JEP hardware monitoring to IS 1 month? May?        
CP/JEP calibration/monitoring 1 month? June??        
CP/JEP subslice tests months? July???        

NB above assumes virtually no more ROD testing required!
JEM simulation ideally needs a joint working visit to sort it out



Tasks and Timescales (3)

PP Subsystem


Activity Duration Date        
PPM module services 2 months? July?????        
PPM simulation 2 months? July?????        
ROD simulation for PPM 1 month? July?????        



Timescale problems

Whats good

Whats necessary

Whats not good



People

Some hope...?

DIG training



Supported Test Plans

What we envisage the software will (and wont) do



next up previous
Murrough Landon (m.p.j.landon@qmul.ac.uk)