Hardware
People
Say 5 months from now to start of slice tests (1 Sep 2001).
We have roughly 4.5 FTEs (plus Oliver?).
Available effort is about 22 FTE*months.
By end of slice tests (31 Mar 2002) about 45 FTE*months.
By TDAQ integration (1 Jun 2002) about 55 FTE*months.
Guesstimate from task list tables: about 70 FTE*months
(mostly desirable for the slice tests).
NB Guesstimates may be optimistic or pessimistic...