Resources



Hardware



People


Say 5 months from now to start of slice tests (1 Sep 2001). We have roughly 4.5 FTEs (plus Oliver?). Available effort is about 22 FTE*months.


By end of slice tests (31 Mar 2002) about 45 FTE*months.


By TDAQ integration (1 Jun 2002) about 55 FTE*months.


Guesstimate from task list tables: about 70 FTE*months (mostly desirable for the slice tests).


NB Guesstimates may be optimistic or pessimistic...