Murrough Landon - 12 November 1999
- Proposed rack layout
- Cable routing
- Holes in shielding wall
- Status
Current Proposal
- Calo Trigger on upper floor of USA15
- Muon Trigger (and CTP, TTC?) on lower floor
- Calo processor in 14 contiguous racks
- Outlying racks for other services (computers etc)
- Receiver crates at the outside, then preprocessor,
trigger processors at the centre
- EM one side, hadronic the other side
- Receiver crates grouped by detector (social reasons)
- Muon RPC and TGC processors either side of a gap in the racks
- CTP and TTC racks near the centre (maybe upstairs if necessary?)